How Long Does It Take to Build a Pool? A Step-by-Step Timeline for Boerne Homeowners

Austin Cooper

Building a pool is an exciting journey, but many homeowners in Boerne, TX, often wonder: How long does it actually take to build a pool? The answer varies based on factors such as design complexity, weather, and customer preferences. However, on average, it takes about four months from start to finish, with most projects falling between 3 and 6 months. Below, we’ll walk you through the major stages of the pool construction process, providing a realistic timeline and the key factors that can influence it.


1. Design and Planning (1-4 Weeks)

The process begins with designing your dream pool and securing the necessary permits. In Boerne, this phase can be as quick as one week if the design is finalized quickly and there are no delays in permitting. Here’s what to expect:

  • Initial Design: Creating the first version of your pool design can take just a day or two. However, changes to the design—such as adjustments to shape, size, or features—can extend this timeline.
  • Permits: Securing permits in Boerne is typically fast, taking just 1-3 days.
  • HOA Approval: If you live in a community with a homeowners’ association (HOA), you’ll need architectural approval before moving forward. This step can take 2-4 weeks, depending on the HOA’s response time.

2. Site Preparation and Excavation (1 Week)

Once the design and permits are finalized, construction begins with site preparation and excavation. This involves clearing the area, marking the layout, and digging the pool. For most projects, excavation and rebar installation takes about a week.

  • Potential Delays: One challenge specific to Boerne is the hard rock in the ground. If we encounter solid rock during excavation, it can add a few extra days to this phase.

3. Gunite Application (1 Day)

After excavation and rebar are complete, the gunite (a specialized concrete mixture) is applied to form the pool shell. This process usually takes just one day. However, it’s important to allow the gunite to cure for at least 2-3 weeks before moving to the next phase. This curing time ensures the pool shell’s strength and durability.

4. Tile, Coping, and Masonry Work (2-3 Weeks)

Next comes the detailed work of adding tile, coping, and any custom masonry elements. The timeline for this phase depends largely on the complexity of your design:

  • Simple designs may take about 2 weeks.
  • More intricate designs or extensive rock features could take closer to 3 weeks.

5. Decking (1-2 Days)

Once the masonry work is complete, the pool decking is installed. Whether you choose concrete, pavers, or another material, this step usually takes just 1-2 days to complete.

6. Plaster Application (1 Day)

The final interior finish, such as plaster or a pebble surface, is applied in just one day. This is the last major construction step before your pool is filled with water.

7. Filling and Final Touches (1 Week)

After the plaster is applied, the pool is filled with water. During this week, contractors will also complete final touches such as installing equipment, balancing the water chemistry, and ensuring everything is functioning properly.

8. Pool School and Handover (1 Day)

Once your pool is ready, it’s time for the handover. Most pool builders, including those in Boerne, offer a “pool school” to teach homeowners how to maintain their pool. This takes about one day and includes lessons on equipment operation, chemical balancing, and routine maintenance.

For a more in-depth timeline and description of every single phase, click here.


Factors That Can Impact the Timeline

While the steps outlined above provide a general timeline, several factors can influence how long it takes to build your pool:

  1. Design Complexity: Pools with spas, custom water features, or intricate rockwork may take longer to complete.
  2. Weather: Rain and lightning can delay outdoor work, especially during excavation or masonry phases.
  3. Material Availability: While rare, supply chain issues can cause delays in obtaining specific materials or finishes.
  4. Change Orders: Homeowner-requested changes during construction can extend the timeline, especially if they require adjustments to previously completed work.

What Homeowners Should Know

Patience is key when building a pool. While the process may take several months, each step is crucial to ensure the highest quality and longevity of your investment. By understanding the timeline and potential challenges, you can approach the process with realistic expectations and excitement for your future backyard oasis.

If you’re considering building a pool in Boerne, TX, understanding the timeline is just the beginning. A transparent and experienced pool builder will guide you through every step, ensuring you’re informed and confident throughout the process.